GRP cascade and maintenance shafts
9
Shaft diameters
3m–7.5m
Depth of May Road shaft A
~70m
Final May Road module, installed in a single lift
67t
Wastewater tunnel the shafts join
16.2km

The project

The Central Interceptor is Watercare’s 16.2km wastewater tunnel beneath Auckland — the largest wastewater infrastructure project in New Zealand’s history. Working for the Ghella Abergeldie Joint Venture (GAJV), RPC engineered, manufactured, delivered and installed nine GRP cascade and maintenance shafts, from 3m to 7.5m in diameter, that join the tunnel.

In 2020 RPC was awarded the Central Interceptor Cascade Shafts project, recognised as the largest diameter and deepest GRP shafts constructed globally.

The challenge

  • Depth and scale. May Road shaft A is 7.5m in diameter and approximately 70m deep — one of the deepest shafts ever to be sunk and lined in the Southern Hemisphere — built from 23 segments.
  • Moving very large parts. The 7.5m-diameter segments from Corio were 3.1m high and weighed 12 tonnes each. Each was transported by road in the early hours of the morning, taking up three lanes of traffic with an escort crew of 12 personnel.
  • A five-year programme through a pandemic. Manufacturing began in November 2020, and the project navigated the significant disruptions caused by the Covid-19 pandemic.

What RPC did

Segments were assembled above ground on site, then lowered into the excavated shafts. At May Road, the last five segments were assembled into a module 15.5m high. This 67-tonne module was installed in a single lift, completing the 7.5m diameter by 70m deep GRP cascade structure. The annulus between the rock excavation and GRP modules was then back-filled with concrete by the GAJV team.

At Tawariki, the DN7500 modules, each weighing up to 32 tonnes, use flanged connections that facilitate rapid assembly on site, thereby reducing construction time. Once installed, each module is encased in concrete to create a corrosion-resistant shaft liner with no exposed concrete surfaces.

Selected shafts:

ShaftSizeHighlights
May Road (shaft A)7.5m diameter × ~70m deep23 segments; final 15.5m-high, 67-tonne module installed in a single lift (Dec 2023)
Dundale4.5m diameter × 24m deepTwo segments, 11.33m and 12.2m long, weighing 34 and 26 tonnes; plus a 3m-diameter control chamber
Rawalpindi5.5m diameter × 26.8m deepSegments made in Batam and Corio (2024)
TawarikiDN7500 × ~25m deepModules 8m wide and up to 32 tonnes, flanged for rapid assembly (2025)
Point Erin3.2m diameterThe final shaft; segments from Batam and Corio (Nov 2025)

OneRPC in action

Designed in Seven Hills, R&D works at Broadmeadow and manufactured in Batam, Indonesia and Corio, Victoria, this project showcased our ability to engineer and deliver complex, high-performance composite solutions on a massive scale. The Central Interceptor project has been a living example of our commitment and strategy as a company — OneRPC.

We truly appreciate all the effort and commitment your team has put in to get us to this point. It’s been a remarkable collaboration, where our relationship has grown stronger and stronger and I am sure there is much more to come.

Francesco SaibeneGAJV Project Director · Email to RPC Managing Director Tony Caristo, 2025

Timeline

Project milestones

  1. 2020

    RPC awarded the Central Interceptor Cascade Shafts project.

  2. Nov 2020

    Manufacturing begins.

  3. Jul 2023

    Dundale: 6th GRP cascade shaft (4.5m × 24m) manufactured, delivered and installed.

  4. Aug 2023

    May Road: assembled module of segments 2B, 3A and 3B installed — a lift weight of more than 50 tonnes. Featured in CompositesWorld (USA).

  5. Dec 2023

    May Road shaft A completed: final 15.5m-high, 67-tonne module installed in a single lift.

  6. Jul 2024

    Rawalpindi: final segments for the 5.5m-diameter, 26.8m-deep shaft leave Batam and Corio.

  7. May 2025

    Composites Australia award for Engineering Excellence for large Scale GRP Infrastructure Manufacturing.

  8. Sep 2025

    Tawariki: DN7500 modules, each up to 32 tonnes, installed in the 25m shaft.

  9. Nov 2025

    Point Erin: final segments of the final shaft depart Batam and Corio.

Gallery

Project news

Updates from the project

All news
Point Erin GRP cascade shaft segment on a transport trailer

Infrastructure

Significant Milestone – Point Erin

Last week we celebrated a significant milestone at RPC with the final two (section 1 and 4) segments of the Point Erin 3.2 diameter shaft departing from our manufacturing facility in Batam, Indonesia.

Looking down the Tawariki shaft during installation

Infrastructure

Tawariki GRP cascade shaft Installation

RPC Technologies has recently installed the first 4 segments of the Tawariki GRP cascade shaft as part of Watercare’s Central Interceptor project in Auckland, New Zealand.