Case studies

Landmark projects

15m GRP dome cover for the Belmont desalination ocean intake, assembled on site

InfrastructureBelmont, NSW · 2025–2026

Belmont Desalination Plant

Scope, design, engineering, manufacture, delivery and site assembly of a 15m-diameter GRP cover operating 20m below sea level, for the direct ocean intake at Hunter Water's new desalination plant.

Diameter dome cover
15m
Below sea level
20m
Plant capacity, rainfall-independent
30 ML/day
VLocity GRP nose cone in production at Corio

TransportCorio, Victoria · 2023–2025

VLocity nose cones

46 GRP nose cones to ballistic standard BR566 Type 2, infused in one piece, assembled and painted at Corio, completing a fleet of 141 regional 3-car trainsets.

Nose cones delivered
46
Ballistic standard
BR566 Type 2
Regional 3-car trainsets in the fleet
141
Rawalpindi shaft segment RW-07 ready for dispatch

InfrastructureAuckland, New Zealand · 2020–2025

Central Interceptor

Design, manufacture, delivery and installation of nine GRP shafts, 3m–7.5m in diameter, joined to the 16.2km wastewater tunnel, the largest wastewater project in NZ history.

GRP cascade and maintenance shafts
9
Shaft diameters
3m–7.5m
Depth of May Road shaft A
~70m
GRP riser for the Alkimos Seawater Desalination Plant being lifted by crane

InfrastructureAlkimos, Perth WA · 2025–2026

Alkimos Seawater Desalination Plant

Three GRP risers, 12–14m long × 1.8m ID, installed offshore in 12–20m of water, and the pre-spooling of approximately 1,100 GRP spools for ASDP Stage 1.

GRP risers, 12–14m long × 1.8m ID
3
Water depth at installation
12–20m
GRP spools pre-fabricated
~1,100
RPC inspector testing a GRP asset, 2026

Asset ServicesSydney, NSW · 2025–2026

Sydney Water asset inspections

UltraAnalytix® condition assessments and Remaining Service Life analysis of 68 FRP tanks across 19 Water Resource Recovery Facilities, without shutdowns or confined-space entry.

FRP tanks assessed
68
Water Resource Recovery Facilities
19
Lowest PDS in the 45-year-old tanks (threshold 40%)
~60%
X'Trapolis 2.0 full-scale mock-up

TransportBroadmeadow, NSW · 2022–2023

Rail mock-ups

Full-scale mock-ups of the X'Trapolis 2.0 train (40m, ~35,000kg) and a fully-operable G Class tram, built at Broadmeadow for stakeholder evaluation.

X'Trapolis 2.0 mock-up: motor car + trailer car
40m
Total mock-up weight
~35,000kg
Stakeholder user groups evaluating the design
60+
St Marys WRRF odour control facility — bio-trickling filters and ducting

InfrastructureSt Marys, Sydney NSW · 2019–2024

St Marys WRRF

Design, manufacture, delivery, installation and commissioning of a complete odour control facility treating 42,900 m³/hr of foul air — bio-trickling filters, carbon units, 1,750m of GRP ducting, covers and stack.

Foul air treated
42,900 m³/hr
GRP ducting, DN100–DN1200
1,750m
Trafficable aluminium and GRP covers
1,500 m²

Project register

Selected projects since 1998

39 projects

Scroll sideways to see all columns.

Project register: year, project, client, business, scope and location
YearProjectClient / partnerBusinessWhat RPC didLocation
2025–26Alkimos SDP Stage 1 risers and pre-spoolingWaterASWA / Water CorporationInfrastructureThree GRP risers + ~1,100 GRP spoolsPerth WA, Australia
2026Barwon Water panelWaterBarwon WaterAsset ServicesFRP condition assessment panelGeelong VIC, Australia
2025–26Belmont Desalination intake coverWaterJohn Holland; Hunter WaterInfrastructure15m GRP dome cover, 20m below sea levelBelmont NSW, Australia
2026Heavy Duty MVDMiningMining customer (unnamed)ProductsNew 2.4m HDMVD productBroadmeadow NSW, Australia
2026NGT tramsTramAlstom; Vic Dept of TransportTransportFront end and roof hood assemblyCorio VIC, Australia
2026Sydney Water FRP tank NDT; OCF maintenanceWaterSydney WaterAsset Services68 tanks across 19 WRRFs; Odour Control Facility optimisationSydney NSW, Australia
ongoingWater Corporation WAWaterWater CorporationAsset ServicesFRP condition assessmentsWA, Australia
2020–25Central InterceptorWastewaterWatercare; GAJVInfrastructureNine GRP cascade shafts, 3m–7.5m diameterAuckland, New Zealand
2024–25KCT soy sauce factoryFood / industrialKwong Cheong ThyeInfrastructure53 FRP tanks (47 round 2.5–3m dia × 6.5–17.5m high + 6 rectangular)Singapore (made in Batam), Singapore
2023–25VLocity nose conesRailAlstom; V/LineTransport46 GRP nose cones to ballistic standard BR566 Type 2Corio VIC, Australia
2024Keppel Sakra Cogen (600MW, hydrogen-ready)EnergyKeppelInfrastructureGRP seawater cooling pipe up to 2.8m diameterJurong Island, Singapore
2022–24Maribyrnong Main Sewer UpgradeWastewaterMelbourne Water; SFPJVInfrastructure4m × 38m GRP maintenance shaft (Batam + Corio)Melbourne VIC, Australia
2024Sembcorp CCP4 (600MW) — Phase 2EnergyJurong Engineering Ltd (JEL)InfrastructureMain CW pipe up to 2.4m diameter + auxiliary CW (RPC also supplied Phase 1 CCP3, 2014)Jurong Island, Singapore
2019–24St Marys WRRF odour control facilityWastewaterSydney Water / AdaptJVInfrastructureComplete odour control facilitySydney NSW, Australia
2023G Class tram mock-upTramAlstomTransportFully-operable mock-upBroadmeadow NSW, Australia
2023PT Amman Batu Hijau CCPP-1 (450MW)EnergyJEL / PT JEL; PT Amman MineralInfrastructure~900m PN6 GRP pipe DN50–DN1100, fittings, supports; full engineering packageSumbawa, Indonesia
2023Ship hull tank test modelsMarineSolution Engineering (Malaysia)Products1:100 VLCC and 1:70 FPSO GRP hullsBatam, Indonesia
2022–23X'Trapolis 2.0 mock-upRailAlstom; Vic DTPTransportFull-scale motor + trailer car mock-upBroadmeadow NSW, Australia
2021Hsinta Power Station extension (Units 1–3)EnergyGEInfrastructureCooling water piping (designed Sydney, made Batam, project managed from Singapore)Taiwan
2021Perth Metronet DMU (Australind replacement)RailAlstom; WA PTATransportSanitary toilet modules incl. tanks, kits and final assemblyPerth WA, Australia
2020Coombabah STP Stage 6WastewaterAcciona; AZZUROInfrastructureOdour control: 3 bio-trickling filters, 800m duct, 600 m² coversGold Coast QLD, Australia
2020Lower Molonglo WWTPWastewaterIcon WaterInfrastructure20m self-supporting, perimeter-bolted GRP tank cover lifted in one pieceACT, Australia
pre-2020Amaroo Sewer Main; Carlton Sewer Upgrade; Princes St manholeWastewaterYarra Valley Water; Melbourne Water; JHGInfrastructureGRP manholes and shaftsMelbourne VIC, Australia
2019Epping Main Sewer UpgradeWastewaterYarra Valley Water; JHGInfrastructure2 × DN3200 + 2 × DN4000 PermaManhole liners, 38–40m deepMelbourne VIC, Australia
2018–19Haughton Pipeline DuplicationWaterTownsville City Council; IplexInfrastructureFittings made at a new Townsville facilityTownsville QLD, Australia
2019Tambak Lorok CCPP Block 3EnergyIndonesia PowerInfrastructure2.4m GRP cooling water pipe, hydrostatic testingSemarang, Indonesia
2017–18HawkeiDefence (Land)Thales AustraliaDefenceFully functional dashboard assemblies (Land 121 Phase 4)Corio VIC, Australia
2018Hunter Class frigates (SEA5000)Defence (Sea)BAE Systems; Tods Defence UKDefencePartnership to deliver sonar domes and composite items—, Australia
2014–18Riviera motor yachtsMarineRiviera AustraliaProductsCNC patterns, moulds and first-off partsBatam, Indonesia
2017Batang coal-fired power stationsEnergy—Infrastructure3.9m × 12.75m GRP cooling water pipes, 12km of pipe and fittings (~1,000 pipes)Central Java, Indonesia
2017Bulimba Creek Sewer Upgrade Stage 2WastewaterQUU; Abergeldie–Obayashi JVInfrastructurePermaManholes (jacking pipe by RPC Pipe Systems, since divested)Brisbane QLD, Australia
2003 / 2017Collins Class submarinesDefence (Sea)Australian DefenceDefenceAcoustic windows at commissioning; re-engineered DA acoustic window sets for LOTEBroadmeadow NSW, Australia
2017Land 121 Phase MH3BDefence (Land)Rheinmetall MAN (RMMVA); Mecprotec OyDefencePrototype of new handling equipment under exclusive licence—, Australia
2015–BHP Olympic DamMiningBHPInfrastructureSite services and maintenance contractRoxby Downs SA, Australia
2011–12Sea Urchin SU550 tidal turbineRenewables—InfrastructureComposite structures; 3 Engineering Excellence Awards (Newcastle)NSW, Australia
1998BHP Whyalla AirfinesMining / industrialBHP; Voest Alpine Industries (VAI)Infrastructure2 × wet gas scrubbers 8.2m × 26m; exhaust stack 3.8m × 100m — the largest GRP structures ever manufactured in AustraliaWhyalla SA, Australia
—Hobsons Bay Sewer UpgradeWastewaterMelbourne WaterInfrastructureVortex structure / shaftsMelbourne VIC, Australia
—India RRTS/MTRS, Sydney Metro, Montreal REM front endsRailAlstomTransportComposite front endsIndia
—Subiaco WWTPWastewaterJohn HollandInfrastructureCovers and ductPerth WA, Australia

Talk to the experts.